HP High Court Directs Power Board to Decide Meter Installation Plea Within Two Days, Seek Police Aid if Needed
SHIMLA — The Himachal Pradesh High Court has directed state power authorities to swiftly decide a petitioner’s plea for an electricity meter installation, reiterating that the electricity board—not the applicant—is responsible for overcoming third-party obstructions.
Justice Sandeep Sharma passed the oral order on November 27, 2026, while disposing of a writ petition (CWP No. 21415 of 2026) filed by Rajesh Kumar Sharma against the Himachal Pradesh State Electricity Board (HPSEB) and others.
Dispute Over Meter Installation
According to the petitioner, repeated requests to have an electricity meter installed at his premises went unfulfilled, prompting him to approach the High Court. During proceedings, counsel for the petitioner submitted on instructions that the local Executive Engineer had agreed to install the meter subject to compliance requirements, but alleged that Sohan Lal and others were creating unnecessary hurdles.
Senior Advocate Sunita Sharma, appearing for the respondents, acknowledged that providing an electricity connection subject to compliances is the duty of the electricity department. She stated on instructions that Sohan Lal had objected to the installation citing pending civil litigation—though the petitioner is not a party to those proceedings.
Two-Day Timeline and Precedent Cited
Without calling for a formal reply or entering into the merits of the dispute, the court disposed of the petition with a direction to respondents 3 and 4 to consider and decide the meter installation application expeditiously, preferably within two days.
Justice Sharma instructed the authorities to follow the court's earlier ruling of September 10, 2026, in Veena Thakur vs. HP State Electricity Board and Others (CWP No. 10203 of 2024). Under the Electricity Act and rules framed thereunder, the order noted:
An applicant is only required to provide necessary assistance, while action to remove obstructions rests with the electricity board.
If an owner, occupier, or person in charge of land objects to work carried out by a licensee, the licensee may obtain written permission from the District Magistrate, Commissioner of Police, or other authorized officers—meaning authorities can seek police assistance if required to install the petitioner's meter.