SHIMLA- SJVN’s 1320 MW Buxar Thermal Power Project in Bihar achieved another milestone today with Jacking up of Ceiling Girder (1400 tonnes) for first boiler Unit.

The activity was virtually activated by Nand Lal Sharma, Chairman & Managing Director from the Company’s Corporate Headquarter at Shimla.

Sharma informed that with this Jacking-up activity, First Boiler Unit of the Project will start taking its shape. He said that the entire process will be completed in Four Stages and in each Stage Ceiling Girder will jack up and jack down to add Pressure Parts and other Components in the Boiler Assembly.

Sharma reiterated the commitment of STPL to complete the project as per schedule in  June 2023 for First Unit & January 2024 for Second Unit. Sharma further informed that Capital Expenditure of Rs. 4617.45 Crore has already been incurred on the project.  During year 2021-22, a capital expenditure of Rs. 2619.06 Crore has been incurred till date. The Project is being constructed at an estimated cost of Rs.10, 439.09 crores, he added.

Facebook Twitter Whatsapp Insta Email Print
Latest Stories
Feb 23
Feb 21
96 Drug Traffickers Nabbed under Anti-Chitta Drive in Himachal

96 Drug Traffickers Nabbed as Himachal Police Tigh...

Feb 21
India-US Army Set to Put Himachal on World's Super Power Map

World Top Military Power land in Himachal